The Postcard
A postally unused postcard bearing no publisher's name. The card has an undivided back.
The Howrah Bridge
The Howrah Bridge is a balanced cantilever bridge over the Hooghly River in West Bengal. Commissioned in 1943, the bridge was originally named the New Howrah Bridge, because it replaced a pontoon bridge at the same location linking the cities of Howrah and Kolkata (Calcutta).
On the 14th. June 1965, it was renamed Rabindra Setu after the great Bengali poet Rabindranath Tagore, who was the first Indian and Asian Nobel laureate. However it is still popularly known as the Howrah Bridge.
The bridge is one of four on the Hooghly River, and is a famous symbol of Kolkata and West Bengal. It carries a daily traffic of approximately 100,000 vehicles and more than 150,000 pedestrians, easily making it the busiest cantilever bridge in the world.
The third-longest cantilever bridge at the time of its construction, the Howrah Bridge is currently the sixth-longest bridge of its type in the world.
History of the Howrah Bridge
In view of the increasing traffic across the Hooghly river, a committee was appointed in 1855–56 to review alternatives for constructing a bridge across it. The plan was shelved in 1859–60.
In 1862, the Government of Bengal asked George Turnbull, chief engineer of the East Indian Railway Company to study the feasibility of bridging the Hooghly River. He had recently established the company's rail terminus in Howrah.
He reported on the 19th. March, with large-scale drawings and concluded that:
-- The foundations for a bridge at Calcutta would be at a considerable depth and cost because of the depth of the mud there.
-- The impediment to shipping would be considerable.
-- A good place for the bridge was at Pulta Ghat, about a dozen miles north of Calcutta, where a bed of stiff clay existed at no great depth under the river bed.
-- A suspended-girder bridge of five spans of 401 feet (122 m) and two spans 200 feet (61 m) would be ideal.
In 1868 it was decided that a bridge should be constructed, and a newly appointed trust vested to manage it. The Calcutta Port Trust was founded in 1870, and the the Howrah Bridge Act was passed in 1871, empowering the lieutenant-governor to have the bridge constructed with Government capital.
A contract was signed with Sir Bradford Leslie to construct a pontoon bridge. This was the bridge that gave its name to the Ghat.
Different parts of the bridge were constructed in England and shipped to Calcutta, where they were assembled. The assembling period was fraught with problems. The bridge was considerably damaged by the great cyclone of the 20th. March 1874.
A steamer named Egeria broke from her moorings and collided head-on with the bridge, sinking three pontoons and damaging nearly 200 feet of the bridge.
The bridge was completed in 1874, and opened to traffic on the 17th. October of that year. The bridge was then 1528 ft long and 62 ft wide, with 7-foot wide pavements on either side.
Initially the bridge was periodically unfastened to allow steamers and other marine vehicles to pass through. Before 1906, the bridge used to be undone for the passage of vessels during daytime only.
Since June of that year it started opening at night for all vessels except ocean steamers, which were required to pass through during daytime. From the 19th. August 1879, the bridge was illuminated by electric lamp-posts, powered by the dynamo at the Mullick Ghat Pumping Station.
Plans for a New Bridge
As the bridge could not handle the rapidly increasing load, the Port Commissioners started planning in 1905 for a new improved bridge.
In 1906 the Port Commission appointed a committee headed by R.S. Highet, chief engineer, East Indian Railway and W.B. MacCabe, chief engineer, Calcutta Corporation. They submitted a report stating that:
-- Bullock carts formed eight-thirteenths of the vehicular traffic across the existing bridge.
--The roadway on the existing bridge is 48 feet wide. The roadway on the new bridge would be wide enough to take at least two lines of vehicular traffic and one line of trams in each direction and two roadways each 30 feet wide, giving a total width of 60 feet of roadway which would be quite sufficient.
-- The traffic across the existing floating bridge between Calcutta & Howrah is very heavy and it is obvious if the new bridge is to be on the same site as the existing bridge, then unless a temporary bridge is provided, there will be serious interruptions to the traffic while existing bridge is being moved to one side to allow the new bridge to be erected on the same site as the present bridge.
The committee eventually decided on a floating bridge. It extended tenders to 23 firms for its design and construction. Prize money of £3,000 was declared for the firm whose design would be accepted.
The initial construction of the bridge was stalled due to the Great War, although the bridge was partially renewed in 1917 and 1927.
In 1921 a committee of engineers named the 'Mukherjee Committee' was formed, headed by R. N. Mukherjee, Sir Clement Hindley, and J. McGlashan, Chief Engineer. They referred the matter to Sir Basil Mott, who proposed a single span arch bridge.
In 1922, the New Howrah Bridge Commission was set up, to which the Mukherjee Committee submitted its report. In 1926 the New Howrah Bridge Act was passed. Messrs. Rendel, Palmer and Tritton were asked to consider the construction of a suspension bridge of a particular design prepared by their chief draftsman Mr. Walton.
On basis of the report, a global tender was issued. The lowest bid came from a German company, but due to increasing political tensions between Germany and Great Britain in 1935, it was not given the contract.
The Braithwaite, Burn & Jessop Construction Co. was awarded the construction contract that year, and construction of the bridge started the following year.
Construction of the New Bridge
The bridge does not have nuts and bolts, but was formed by riveting the whole structure. It consumed 26,500 tons of steel, out of which 23,000 tons of high-tensile alloy steel, known as Tiscrom, were supplied by Tata Steel.
The main tower was constructed with single monolith caissons of dimensions 55.31 m × 24.8 m with 21 shafts, each 6.25 metres square. Work could not be started because of the Great War.
Then in 1926 a commission under the chairmanship of Sir R. N. Mukherjee recommended a suspension bridge of a particular type to be built across the River Hooghly. The bridge was designed by Mr. Walton of M/s Rendel, Palmer & Triton.
However World War II (1939–1945) intervened. All the steel that was to come from England was diverted for war effort in Europe. Out of the 26,000 tons of steel, that was required for the bridge, only 3000 tons was supplied from England.
In spite of the Japanese threat, the then (British) government of India pressed on with the construction. Tata Steel were asked to supply the remaining 23,000 tons of high tension steel. The Tatas developed the quality of steel required for the bridge and called it Tiscom. The entire 23,000 tons was supplied in time.
The fabrication and erection work was awarded to a local engineering firm of Howrah: the Braithwaite, Burn & Jessop Construction Co. The two anchorage caissons were each 16.4 m by 8.2 m, with two wells 4.9 m square. The caissons were so designed that the working chambers within the shafts could be temporarily enclosed by steel diaphragms to allow work under compressed air if required.
The caisson at the Kolkata side was set at 31.41 m and that at Howrah side at 26.53 m below ground level.
One night, during the process of excavating the muck to enable the caisson to move, the ground below it yielded, and the entire mass plunged two feet, shaking the ground. The impact of this was so intense that the seismograph at Kidderpore registered it as an earthquake, and a Hindu temple on the shore was destroyed, although it was subsequently rebuilt.
While muck was being cleared, numerous objects were brought up, including anchors, grappling irons, cannons, cannonballs, brass vessels, and coins dating back to the East India Company. The job of sinking the caissons was carried out round-the-clock at a rate of a foot or more per day. The caissons were sunk through soft river deposits to a stiff yellow clay 26.5 m below ground level.
The accuracy of sinking the huge caissons was exceptionally precise, within 50–75 mm of the true position. After penetrating 2.1 m into clay, all shafts were plugged with concrete after individual dewatering, with some 5 m of backfilling in adjacent shafts.
The main piers on the Howrah side were sunk by open wheel dredging, while those on the Kolkata side required compressed air to counter running sand. The air pressure maintained was about 40 lbs per square inch (2.8 bar), which required about 500 workers to be employed.
Whenever excessively soft soil was encountered, the shafts symmetrical to the caisson axes were left unexcavated to allow strict control. In very stiff clays, a large number of the internal wells were completely undercut, allowing the whole weight of the caisson to be carried by the outside skin friction and the bearing under the external wall. The work on the foundation was completed in November 1938.
By the end of 1940, the erection of the cantilevered arms was commenced and was completed in mid-summer of 1941. The two halves of the suspended span, each 282 feet (86 m) long and weighing 2,000 tons, were built in December 1941.
The bridge was erected by commencing at the two anchor spans and advancing towards the center, with the use of creeper cranes moving along the upper chord. 16 hydraulic jacks, each of which had an 800-ton capacity, were pressed into service to join the two halves of the suspended span.
The entire project cost £2,463,887. The project was a pioneer in bridge construction, particularly in India, but the government did not have a formal opening of the bridge due to fears of attacks by Japanese planes fighting the Allied Powers. Japan had attacked the United States at Pearl Harbor on the 7th. December 1941. The first vehicle to use the bridge was a solitary tram.
The bridge is a suspension-type balanced cantilever bridge, with a central span 1,500 feet (460 m) between centers of main towers and a suspended span of 564 feet (172 m). The main towers are 280 feet (85 m) high above the monoliths and 76 feet (23 m) apart at the top.
The anchor arms are 325 feet (99 m) each, while the cantilever arms are 468 feet (143 m) each. The bridge deck hangs from panel points in the lower chord of the main trusses with 39 pairs of hangers. The roadways beyond the towers are supported from ground, leaving the anchor arms free from deck load.
The deck system includes cross girders suspended between the pairs of hangers.
The longitudinal expansion and lateral sway movement of the deck are taken care of by expansion and articulation joints. There are two main expansion joints, one at each interface between the suspended span and the cantilever arms and there are others at the towers and at the interface of the steel and concrete structures at both approaches.
The bridge deck has longitudinal ruling gradient of 1 in 40 from either end, joined by a vertical curve of radius 4,000 feet (1,200 m).
Bridge traffic
In 1946, a census of the daily traffic was taken, which counted 27,400 vehicles, 121,100 pedestrians and 2,997 cattle. The bulk of the vehicular traffic comes from buses and cars. Prior to 1993, the bridge also carried trams.
However, the bridge still continues to carry much more than the expected load. A 2007 report revealed that nearly 90,000 vehicles were plying on the bridge daily (15,000 of which were goods-carrying), though its load-bearing capacity is only 60,000. The road is flanked by footpaths 15 feet (4.6 m) wide, which are thronged with pedestrians.
Maintenance of the Bridge
The bridge has been subject to damage from vehicles due to rash driving, and corrosion due to atmospheric conditions and biological wastes. In October 2008, 6 high-tech surveillance cameras were placed to monitor the entire structure from a control room. This was in response to substantial damage caused to the bridge by collisions with vehicles, so that compensation could be claimed from the miscreants.
Corrosion has been caused by bird droppings and human spitting. An investigation in 2003 revealed that as a result of prolonged chemical reaction caused by continuous collection of bird excreta, several joints and parts of the bridge were damaged. As an immediate measure, the Kolkata Port Trust engaged contractors to regularly clean the bird droppings, at an annual expense of US$6,300.
In 2004, KoPT spent US$81,000 to paint the 2.2 million square metres of the bridge, requiring a total of 26,500 litres of paint.
The bridge is also considerably damaged by pedestrians spitting out acidic, lime-mixed stimulants (gutka and paan). An inspection by Port Trust officials in 2011 revealed that spitting had reduced the thickness of the steel hoods protecting the pillars from six to less than three millimeters since 2007.
The hangers need those hoods at the base to prevent water seeping into the junction of the cross-girders and hangers, and damage to the hoods can jeopardize the safety of the bridge. KoPT announced that it will spend US$25,000 on covering the base of the steel pillars with fibreglass casing to prevent spit from corroding them.
On the 24th. June 2005, a private cargo vessel M V Mani, while trying to pass under the bridge during high tide, had its funnel stuck underneath for three hours, causing substantial damage to the bridge. The damage was so severe that KoPT requested help from Rendall-Palmer & Tritton Limited, the original consultant on the bridge from the UK.
KoPT also insisted on the use of steel matching that used during the bridge's construction in 1943. For the repair, which cost around US$63,000, about 8 tonnes of steel was used. The repairs were completed in early 2006.